About a week for a typical site of up to about seven pages, especially when the design already exists. You get a private preview link within the first few days, a review round, and then we switch the DNS together. Larger sites with many templates, a blog to move or custom integrations take longer, and the quote says how long.
A typical week
- Day 1: kickoff. I collect the design or current site, logos, and access to the DNS (or we change the records together on a short screen share).
- Days 2 and 3: the build. The preview link goes to you as it comes together.
- Day 4: your review round, on your own phone and computer.
- Day 5: your IT review if you have one, then the DNS switch. The old records are kept so a rollback is instant.
Horizon Home Buyers was rebuilt and switched over on the same day. A site with a large blog or several integrations takes longer, and the written quote gives you the schedule.